Tower Electric and Magnetic Fields Title
 

400 kV overhead lines: electric field

see also:

400 kV is the highest voltage in use in the UK.

The maximum field is produced by the largest design of line – the L6 – when the ground clearance is the minimum allowed – 7.6 m. The field also depends on the phasing. Untransposed (U) is generally higher and is shown here.

Typical fields are lower than the maximum field because the clearance is usually higher. Also, many lines are a slightly smaller design – the L2.  Both L6 and L2 are shown on the following graph.  The phasing here is transposed (T) as this is more common.

Larger 400 kV pylon (L6):  Smaller 400 kV pylon (L2):

This table gives some actual field values for the same conditions.

         

electric field in V m-1 at distance from centreline

maximum under line

10 m

25 m

50 m

100 m

400 kV

largest lines

L6
quad bundles
0.305 m
zebra

maximum

clearance 7.6 m
phasing U

11400

10130

774

446

156

typical

clearance 13 m
phasing T

4244

4206

962

106

32

smaller lines

L2
twin bundles
0.305 m
zebra

maximum

clearance 7.6 m
phasing U

9897

6618

283

357

118

typical

clearance 13 m
phasing T

3128

2964

469

56

27

typical design used for new lines

L12
twin bundles
0.5 m
araucaria

maximum

clearance 7.6 m
phasing U

10642

8410

669

404

136

clearance 7.6 m
phasing T

9384

7933

737

151

30

typical

clearance 13 m
phasing T

3704

3595

732

98

26

Note:

1. All fields calculated at 1 m above ground level.

2. All electric fields are calculated for the nominal voltage.  In practice, voltages (and hence fields) may rise by a few percent.

3. All electric fields calculated here are unperturbed values.

4. All fields are given to the same resolution for simplicity of presentation (1 V/m) but are not accurate to better than a few percent.

5. Calculations ignore zero-sequence voltages.  This means values at larger distances are probably underestimates, but this is unlikely to amount to more than a few percent and less closer to the line.

6. The “maximum field under the line” is the largest field, which is not necessarily on the route centreline; it is often under one of the conductor bundles.

7. In efforts to reduce aerodynamic problems, a small number of 400 kV lines with quad bundles have had expanded bundles fitted, eg 500 mm horizontally.  This produces slightly higher electric fields but is not included in these tables.

8. Calculated fields agree well with measured fields.  more