Tower Electric and Magnetic Fields Title
 

Overhead Lines

Tables of calculated magnetic fields produced by overhead lines in operation in the UK

See also the companion tables for electric fields, underground fields and the simpler summary.

         

magnetic field in µT at distance from centreline

maximum under line

10 m

25 m

50 m

100 m

400 kV

and

275 kV

largest lines

L6
quad bundles
0.305 m
zebra

maximum

clearance 7.6 m
phasing U
load 4.7/4.7 kA

108.422

95.780

38.422

11.697

3.096

typical

clearance 13 m
phasing T
load 0.4/0.6 kA

5.783

5.247

2.194

0.578

0.119

smaller lines

L2
twin bundles
0.305 m
zebra

maximum

clearance 7.6 m
phasing U
load 2.4/2.4 kA

54.142

46.300

16.283

4.865

1.278

typical

clearance 13 m
phasing T
load 0.4/0.6 kA

4.971

4.158

1.557

0.400

0.084

typical design used for new lines

L12
twin bundles
0.5 m
araucaria

maximum

clearance 7.6 m
phasing U
load 3.5/3.5 kA

81.942

72.818

22.103

8.148

2.145

typical

clearance 13 m
phasing T
load 0.4/0.6 kA

5.604

4.938

1.979

0.514

0.106

132 kV

and

66 kV

largest lines

L7
twin bundles
0.305 m
lynx

maximum

clearance 7 m
phasing U
load 1.4/1.4 kA

30.445

20.532

5.553

1.528

0.392

typical

clearance 10 m
phasing U
load 0.13/0.13

1.848

1.359

0.468

0.138

0.036

smaller lines

L132
single conductors
0.4 sq in

maximum

clearance 7 m
phasing U
load 1.2/1.2 kA

24.585

17.217

4.587

1.247

0.318

typical

clearance 10 m
phasing U
load 0.13/0.13 kA

1.731

1.317

0.451

0.132

0.034

smallest wood-pole design

trident
150 m span
single conductors
lynx

maximum

clearance 7 m
single circuit
load 0.7 kA

12.347

12.347

0.738

0.192

0.048

typical

clearance 10 m
single circuit
load 0.1 kA

1.764

0.385

0.099

0.027

0.007

33 kV

larger lines on steel pylons

D
single conductors
r=9.8 mm

maximum

clearance 5.5 m
phasing U
load 1/1 kA

25.686

10.742

2.274

0.594

0.150

typical

clearance 8 m
phasing U
load 0.1 kA

1.556

0.822

0.214

0.058

0.015

smaller lines on wood poles

wood pole
horizontal array
+-2 m

maximum

clearance 5.5 m
single circuit
load .5 kA

14.748

2.961

0.541

0.138

0.035

typical

clearance 8 m
single circuit
load 0.1 kA

1.325

0.471

0.103

0.027

0.007

11 kV

larger lines on steel pylons

SL11
single conductors

maximum

clearance 5.5 m
phasing U
load 0.5/0.5 kA

9.456

7.664

1.490

0.364

0.090

typical

clearance 8 m
phasing U
load 0.1 kA

1.004

0.942

0.274

0.071

0.018

smaller lines on wood poles

wood pole
horizontal array
+-1.15 m

maximum

clearance 5.5 m
single circuit
load 0.2 kA

3.744

0.668

0.124

0.032

0.008

typical

clearance 8 m
single circuit
load 0.05 kA

0.399

0.134

0.030

0.008

0.002

400 V

wood pole

vertical array
50 mm2

maximum

clearance 5.5 m
single circuit
load 0.2 kA
net 0.01 kA@90

1.227

0.277

0.088

0.041

0.020

typical

clearance 8 m
single circuit
load 0.05 kA
net 0.005 kA@90

0.215

0.099

0.041

0.020

0.010

Notes to table:

1.        Calculations performed on computer programme EM2D by John Swanson January 2005.

2.        Typical phases are T=transposed for 275 kV and 400 kV, U=untransposed for 132 kV and below (phases apply to double-circuit lines only)

3.        For magnetic fields, the phasing which gives the highest field is usually U, but with the exception that close to the centreline at low clearances T can give higher field.  The table uses whichever gives the higher field.

4.        The “maximum field under the line” is the largest field, which is not necessarily on the route centreline; it is often under one of the conductor bundles for a two-circuit line and can even be outside the conductors eg for a 400 V vertical array.

5.        All fields calculated at 1 m above ground level.

6.        All fields are given to the same resolution for simplicity of presentation (1 nT ) but are not accurate to better than a few percent.

7.        Calculations ignore zero-sequence current.  This means values at larger distances are probably underestimates, but this is unlikely to amount to more than a few percent except for 400 V lines.  For lines with transposed phasing, typical loads are entered with an unbalance between the two circuits to approximate realistic conditions.

8.        Generally speaking, the lower the voltage, the more different variants of design there are.  The “maximum” calculation is presented here in good faith but may not take account of every last variant in operation.  To meet specific local circumstances, lines at 132 kV and below may occasionally have been constructed with higher ratings.  Within the legal framework of the Regulations, different DNOs may have different policies regarding minimum clearances.

9.        All calculations are for three-phase lines, single-phase lines at low voltages have not been investigated.

Notes on specific voltages:

1.        For 400 kV, L12 lines are included as these are likely to be used for new construction. Phasing U gives the maximum field under the line and is included for that reason but phasing T would be used in practice so is also included.

2.        275 kV lines use identical constructions to 400 kV therefore for magnetic fields the fields are basically the same.  (This assumes 275 kV lines are built to the same minimum clearance, 7.6 m, as 400 kV lines, rather than the permitted 7.3 m.)

3.        132 kV lines have, in the past, been constructed on 275/400 kV towers with a view to future uprating.  This is unlikely to happen again so is not included here.  Similarly, lines constructed to any voltage may be operated at a lower voltage.

4.        400 V lines: calculations are for open-phase designs.  ABC (aerial bundled conductors) produce lower fields but are not susceptible to easy calculations.

Version 3 12 January 2005

 

back